BlueCollar · Project analytics
Maple Lawn Senior Living: Electrical Package
Data as of Jul 10, 2026
Personalize dashboard
Drag cards to rearrange, click the eye to show or hide them.
Margin health
Projected margin
13.1%
-1.1 pt vs bid 14.2% · recovering from 12.5% in Feb
Current gross profit
$684.8K
14.1% of the $4.85M contract
Projected gross profit
$637.5K
-$47.3K fade · was -$77K at the Feb low
Earned gross profit
$257.4K
13.0% margin on work performed
Gross profit
Earned to date vs current and projected estimates
Financial summary
Contract, cost, and gross profit across estimate stages
| Original | Changes | Current | Projected | Earned to date | To date | To complete |
| Revenue | $4,500,000 | $352,400 | $4,852,400 | $4,852,400 | $1,977,800 | $1,842,300 | $3,010,100 |
| Cost | $3,860,000 | $307,600 | $4,167,600 | $4,214,900 | $1,720,400 | $1,720,400 | $2,494,500 |
| Gross profit | $640,000 | $44,800 | $684,800 | $637,500 | $257,400 | $121,900 | $515,600 |
| GP % | 14.2% | 12.7% | 14.1% | 13.1% | 13.0% | 6.6% | 17.1% |
Cash position
Billed to date
$1.84M
38.0% of current contract
Underbilled
$135.5K
Earned exceeds billed · peak $210K under in Mar
Unbilled retention
$92.1K
5% retainage held to date
Earned revenue
$1.98M
40.8% of current contract
Revenue and billing
Earned vs billed · billed ahead through fall, behind through the winter push, recovering since Apr
Progress and cost
Complete, cost basis
41.3%
Actual cost to date
$1.72M
of the $4.17M current estimate
Committed cost
$2.15M
51.5% of estimate committed
Cost to complete
$2.49M
Projected estimate +$47.3K over current
Cost
Actual and committed cost vs current and projected estimates
All metrics
Every tracked metric, prior month vs current month
| Metric | Prior month | Current month | Change | Change % |